Golden State Water continually invests to maintain and improve the local water systems to ensure the delivery of reliable, quality water is not compromised.

Customers interested in learning more about current and completed infrastructure projects in the Placentia Customer Service Area are encouraged to review the projects listed below.

Current & Upcoming Projects

Linda Vista Reservoir
6591 Kameha Circle in Yorba Linda

Investment: $410,000

Project Timeline:
March 4, 2019 – June 19, 2019

Working Hours:
8 a.m. – 5 p.m.

Construction crews will work to recoat the existing Linda Vista reservoir.

This project will ensure Golden State Water can continue providing reliable water service to local customers.

Click here to view the construction notice.


Fairhaven Well
2048 Fairhaven Avenue

Investment: $3.51 million

Phase 2:

Project Timeline:
June 19, 2019 – January 28, 2020

Primary Working Hours:
TBD
*There will be times during the construction period when around-the-clock (24 hours a day, 7 days a week) operations will be necessary.

Construction crews will work to equip the new water well at the Fairhaven Plant.

This project will improve the distribution
system and ensure Golden State Water can continue providing reliable water service to local customers.

Click here to view the construction notice.

Click here for further project details.

This picture is a map showing construction at 2048 Fairhaven Avenue.
Click on photo to enlarge.

Peacock Hill Reservoir
1311 Peacock Hill Dr.

Investment: $3.43 million

Project Timeline:
November 6, 2017 – September 4, 2019

Working Hours:
Monday – Friday
8 a.m. – 5 p.m.

Construction crews will work to:

  • Install 2 temporary storage tanks to collectively store approximately 250,000 gallons

These temporary storage tanks are needed when we take the Peacock Reservoir out of service to ensure that the water supply in the area is not interrupted.

Click here to view the construction notice.

This is a map showing that construction crews will be working on 1311 Peacock Hill Drive.
Click on photo to enlarge.

Recently Completed Projects

Larkridge Plant
19762 Larkridge Dr.

Investment: $985,500

Project Timeline:
June 5, 2018 – October 2018

Working Hours:
Monday – Friday
8 a.m. – 5 p.m.

Construction crews worked to:

  • Recoat the interior of two 350,000 gallon tanks
  • Install safety appurtenances on the interior and exterior of the reservoir
  • Modify onsite inlet and outlet piping for the reservoirs

These improvements extend the useful life of the reservoirs and allow for their continued safe operation, enabling Golden State Water Company to continue to provide reliable, quality water to our customers.

Click here to view the construction notice.

This map shows construction at 19762 Larkridge Dr.
Click on photo to enlarge.

Orange County
Skyline Dr., between Cowan Heights Dr. and Hunting Horn Dr., and Peacock Hill Dr. west of Skyline Dr.

Investment: $1.8 Million

Project Timeline:
September 18, 2017 – TBD
Working Hours:
8 a.m. – 4 p.m.

Construction crews worked to:

  • Install 3,700 ft. of water pipe
  • Install new water services
  • Install fire hydrants

Click here to read more about the project.
Click here to view the construction notice.

This is a map showing that construction crews will be working on Skyline Drive and Peacock Hill Dr.
Click on photo to enlarge.

Cowan Heights
La Verada Dr., between Skyline Dr. to the La Vereda Plant, and East Lemon Heights Dr., between Sharon Ln. to the west of Maverick Ln.

Investment: $793,000

Project Timeline:
Late June 2017 – September 2017

Construction crews worked to:

  • Install 1,600 ft. of new water pipe

Click here to view the construction notice.

This is a map showing that construction crews
previous arrow
next arrow
Slider

Click on photo to enlarge.

Placentia
Melrose St., Center St., Main St., Aguirre Ln. and Chapman Ave.

Project Timeline:
August 1, 2016 – October 15, 2016

Working Hours:
7 a.m. – 4:30 p.m.

Construction crews worked to:

  • Install new water pipe
  • Install new service lines
  • Install fire hydrants

Click here to view the construction notice.

This is a map showing that construction crews worked on Melrose Street, Main Street, Center Street, Aguirre Lane and Chapman Avenue.

*This list highlights some of the significant infrastructure projects in the Placentia Customer Service Area.