Capital Projects
More than $9.2 million in infrastructure improvements are planned for 2022 in the Santa Maria service area.
The 2022 investments include water supply enhancements, distribution and ongoing improvements designed to replace old meters, mains and safety equipment. Click here to learn more and access a list of projects planned for 2022.
Current & Upcoming Projects
This section is currently under construction. Please check regularly for the latest updates!
Recently Completed Projects
Lake Marie Reservoir Liner
Investment:
$260,000
Project Timeline:
November 2019 – Feb. 7, 2020
Construction crews worked to replace the existing liner in the Lake Marie reservoir.
This project will ensure Golden State Water can continue
providing reliable water service to local customers.
Alta Mesa Well
1710 Via Alta Mesa in Nipomo
Investment:
$820,000
Project Timeline:
Feb. 4, 2019 – Dec. 11, 2019
Working Hours:
TBD
Construction crews will work to install a water filtration system.
This project will ensure Golden State Water can continue
providing reliable water service to local customers.
Portable Generator & Generator
Connector
Systemwide
Investment:
$266,000
Project Timeline:
Sept. 18, 2018 – Feb. 29, 2020
Working Hours:
Monday – Friday
7 a.m. – 4 p.m.
Construction crews will work to install and connect emergency generators throughout the system.
This project will ensure Golden State Water can continue
providing reliable water service to local customers during
site-specific power outages.
SCADA System
Cypress Ridge System
Investment:
$1 million
Project Timeline:
July 1, 2019 – Spring 2020
Construction crews will work to install a SCADA system, which will allow for systemwide automation.
This project will ensure Golden State Water can continue
providing reliable water service to local customers during
site-specific power outages.
Pinewood Plant
3599 Pinewood Road
Investment:
$2.6 million
Project Timeline:
Sept. 18, 2018 – Oct. 31, 2019
Working Hours:
Monday – Friday
8 a.m. – 5 p.m.
Construction crews worked to:
- Construct 238,000-gallon welded steel tank
- Construct booster station
This project will increase the water storage capacity for the Tanglewood System.
View the construction notice.
Oak Plant
210 Oak Street in Orcutt
Investment:
$330,000
Project Timeline:
April 12, 2019 – June 19, 2019
Working Hours:
Monday – Friday
7 a.m. – 4 p.m.
Construction crews worked to upgrade the well.
This project will improve the distribution system and ensure
Golden State Water can continue providing reliable water service
to local customers.
Orcutt Hill Plant
Investment:
$.5 million
Project Timeline:
September 18, 2018 – September 16, 2019
Working Hours:
Monday – Friday
7 a.m. – 5 p.m.
Construction crews worked to recoat the interior of the reservoir.
This project will extend the useful life of the reservoir and
ensure Golden State Water can continue providing reliable water
service to local customers.
Marcum Street
Marcum Street from Clark Avenue to the end
Investment:
$57,500
Project Timeline:
December 10, 2018 – January 9, 2019
Working Hours:
Monday – Friday
7 a.m. – 4 p.m.
Construction crews worked to:
- Install 165 feet of pipe
- Install three services
- Install a new flushout
This project will ensure Golden State Water can continue providing reliable water service to local customers.
View the construction notice.
Orcutt
Derrick Alley from Clark Avenue to Union Avenue.
Investment:
$216,000
Project Timeline:
November 5, 2018 – December 31, 2018
Working Hours:
Monday – Friday
7 a.m. – 4 p.m.
Construction crews worked to:
- Install 350 LF of pipeline
- Install one fire hydrant
- Install 14 services
This project improved the distribution system and ensured Golden State Water can continue providing reliable water service to local customers.
View the construction notice.
Orcutt Road
Orcutt Road between Shirley Lane to Lakeview Road and on Lakeview
Road to Marvin Street.
Investment:
$1.2 million
Project Timeline:
July 16, 2018 – September 30, 2018
Working Hours:
Monday – Friday
7 a.m. – 5 p.m.
Construction crews worked to:
- Install 4,300 ft. of pipeline
- Install 5 hydrants
- Install 12 services
This project improved the distribution system and ensured Golden State Water can continue providing reliable water service to local customers.
View the construction notice.
Mira Flores No. 1
280 Pabst Lane, Orcutt, CA
Project Timeline:
August 14, 2017 – January 3, 2018
Working Hours:
Monday – Friday
7 a.m. – 4 p.m.
Construction crews worked to:
Remove and install a new roof for the Mira Flores No. 1
Reservoir
Click here to view the construction notice.
View the construction notice.