Capital Projects

Post

More than $9.2 million in infrastructure improvements are planned for 2022 in the Santa Maria service area.

The 2022 investments include water supply enhancements, distribution and ongoing improvements designed to replace old meters, mains and safety equipment. Click here to learn more and access a list of projects planned for 2022.

Current & Upcoming Projects

This section is currently under construction. Please check regularly for the latest updates!

Recently Completed Projects

Lake Marie Reservoir Liner

Investment:
$260,000

Project Timeline:
November 2019 – Feb. 7, 2020

Construction crews worked to replace the existing liner in the Lake Marie reservoir.

This project will ensure Golden State Water can continue providing reliable water service to local customers.
 

outline of Alta Mesa Well Project

Alta Mesa Well
1710 Via Alta Mesa in Nipomo

Investment:
$820,000

Project Timeline:
Feb. 4, 2019 – Dec. 11, 2019

Working Hours:
TBD

Construction crews will work to install a water filtration system.

This project will ensure Golden State Water can continue providing reliable water service to local customers.
 

Portable Generator & Generator Connector 
Systemwide

Investment:
$266,000

Project Timeline:
Sept. 18, 2018 – Feb. 29, 2020

Working Hours:
Monday – Friday
7 a.m. – 4 p.m.

Construction crews will work to install and connect emergency generators throughout the system.

This project will ensure Golden State Water can continue providing reliable water service to local customers during site-specific power outages.
 

SCADA System
Cypress Ridge System

Investment:
$1 million

Project Timeline:
July 1, 2019 – Spring 2020

Construction crews will work to install a SCADA system, which will allow for systemwide automation.

This project will ensure Golden State Water can continue providing reliable water service to local customers during site-specific power outages.
 

outline of Pinewood Plant Project

Pinewood Plant
3599 Pinewood Road

Investment:
$2.6 million

Project Timeline:
Sept. 18, 2018 – Oct. 31, 2019

Working Hours:
Monday – Friday
8 a.m. – 5 p.m.

Construction crews worked to:

  • Construct 238,000-gallon welded steel tank
  • Construct booster station

This project will increase the water storage capacity for the Tanglewood System.

View the construction notice.
 

outline of Oak Plant Project

Oak Plant
210 Oak Street in Orcutt

Investment:
$330,000

Project Timeline:
April 12, 2019 – June 19, 2019

Working Hours:
Monday – Friday
7 a.m. – 4 p.m.

Construction crews worked to upgrade the well.

This project will improve the distribution system and ensure Golden State Water can continue providing reliable water service to local customers.
 

outline of Orcutt Hill Plant Project

Orcutt Hill Plant

Investment:
$.5 million

Project Timeline:
September 18, 2018 – September 16, 2019

Working Hours:
Monday – Friday
7 a.m. – 5 p.m.

Construction crews worked to recoat the interior of the reservoir.

This project will extend the useful life of the reservoir and ensure Golden State Water can continue providing reliable water service to local customers.
 

outline of Marcum Street Project

Marcum Street
Marcum Street from Clark Avenue to the end

Investment:
$57,500

Project Timeline:
December 10, 2018 – January 9, 2019

Working Hours:
Monday – Friday
7 a.m. – 4 p.m.

Construction crews worked to:

  • Install 165 feet of pipe
  • Install three services
  • Install a new flushout

This project will ensure Golden State Water can continue providing reliable water service to local customers.

View the construction notice.
 

outline of Derrick Alley Project

Orcutt
Derrick Alley from Clark Avenue to Union Avenue.

Investment:
$216,000

Project Timeline:
November 5, 2018 – December 31, 2018

Working Hours:
Monday – Friday
7 a.m. – 4 p.m.

Construction crews worked to:

  • Install 350 LF of pipeline
  • Install one fire hydrant
  • Install 14 services

This project improved the distribution system and ensured Golden State Water can continue providing reliable water service to local customers.

View the construction notice.
 

outline of Orcutt Road Project

Orcutt Road
Orcutt Road between Shirley Lane to Lakeview Road and on Lakeview Road to Marvin Street.

Investment:
$1.2 million

Project Timeline:
July 16, 2018 – September 30, 2018

Working Hours:
Monday – Friday
7 a.m. – 5 p.m.

Construction crews worked to:

  • Install 4,300 ft. of pipeline
  • Install 5 hydrants
  • Install 12 services

This project improved the distribution system and ensured Golden State Water can continue providing reliable water service to local customers.

View the construction notice.
 

outline of Mira Flores No. 1 Project

Mira Flores No. 1
280 Pabst Lane, Orcutt, CA

Project Timeline:
August 14, 2017 – January 3, 2018

Working Hours:
Monday – Friday
7 a.m. – 4 p.m.

Construction crews worked to:

Remove and install a new roof for the Mira Flores No. 1 Reservoir
Click here to view the construction notice.

View the construction notice.