Golden State Water continually invests to maintain and improve the local water systems to ensure the delivery of reliable, quality water is not compromised.

Customers interested in learning more about current and completed infrastructure projects in the Southwest Customer Service Area are encouraged to review the projects listed below.

Current & Upcoming Projects

Click here for more information.

Hawthorne & Inglewood
Atkinson Ave, Chanera Ave, Ardath Ave, Wilkie Ave, from 116th to 119th St, Casimir Ave, from Imperial to 119th St, Purche Ave from 118th Pl to 119th St, Daphne Ave from 118th St to 119th St, Spinning Ave from 115th Pl to 119th St, 115th St from Casimir to Van Ness, 115th Pl and 117th St from Casimir to Spinning, 116th St from Crenshaw to Van Ness, 118th St from Casimir to Daphne, 118th Pl from Casimir to Purche, Haas Ave, Daleside Ave, Cimarron Ave, Tarron Ave off of 120th St, 120th St from Van Ness to Wilton Pl, Van Ness Ave from 120th St to the 105 Fwy, and Crenshaw Blvd from 116th to 119th St.

Investment: $4.7 million

Project Timeline:
June 19, 2018 – November 30, 2018

Working Hours:
City of Hawthorne:
Monday – Friday (No weekends or holidays)
8:30 a.m. – 3:30 p.m. (8:30 a.m. – 2:30 p.m. when working near schools)

City of Inglewood:
Monday – Friday (No weekends or holidays)
8:30 a.m. – 4:00 p.m.

Construction crews will work to:

  • Install 17,600 LF of 8” main
  • Install 30 fire hydrants
  • Install 485 services

This project will improve the distribution
system and ensure Golden State Water can continue providing reliable water service to local customers.

Click here for more information.


147th and Dublin Area Main Replacement Phase 1
Area bounded by 144th Street, Wadkins Avenue, 147th Street and Van Ness.

Investment: $3,460,368

Project Timeline:
June 18, 2018 – January 2019

Working Hours:
Monday – Friday (No weekends or holidays)
8:00 a.m. – 4:00 p.m.

Construction crews will work to:

  • Install 14,105 LF of 6” and 8” main
  • Install 24 fire hydrants
  • Install 342 services

This project will improve the distribution
system and ensure Golden State Water can continue providing reliable water service to local customers.


 

Shoup
129th, 131st, 133rd, 134th and 141st Streets from La Cienega Blvd. to Inglewood Ave.; on 130th and 140th from Ocean Gate Ave. to Inglewood Ave., on 135th and 138th Streets from Shoup Ave. to Inglewood Ave., on Shoup Ave. from El Segundo Blvd. to 134th Street and from 140th Street to 141st Street, and at the intersection of 132nd Street and Ocean Gate Ave.

Investment: $4.1 million

Project Timeline:
June 4, 2018 – December 2018

Working Hours:
Monday – Friday (No weekends or holidays)
7:00 a.m. – 4:00 p.m.

Construction crews will work to:

  • Install more than 3.6 miles (19,400 LF) of new PVC pipe
  • Install water services
  • Install fire hydrants

This project will improve the distribution
system and ensure Golden State Water can continue providing reliable water service to local customers.

Click here to view the construction notice.

This image is a map showing construction on 129th, 131st, 133rd, 134th and 141st Streets from La Cienega Blvd. to Inglewood Ave.; on 130th and 140th from Ocean Gate Ave. to Inglewood Ave., on 135th and 138th Streets from Shoup Ave. to Inglewood Ave., on Shoup Ave. from El Segundo Blvd. to 134th Street and from 140th Street to 141st Street, and at the intersection of 132nd Street and Ocean Gate Ave.

Inglewood
2850 W. Imperial Hwy

Investment: $32,322

Project Timeline:
May 7, 2018 – mid-June, 2018

Working Hours:
Monday – Friday (No weekends or holidays)
8:00 a.m. – 4:00 p.m.

Construction crews will work to:

  • Install and furnish 1″ service lines
  • Install and furnish 2″ service lines
  • Install and furnish 6″ fire service

This project will further support in providing reliable and quality water.

Click here to view the construction notice.

This is a map showing that construction crews will be working on Imperial Highway.

Los Angeles
4952 W. 112th Street

Investment: $32,322

Project Timeline:
May 7, 2018 – mid-June, 2018

Working Hours:
Monday – Friday (No weekends or holidays)
8:00 a.m. – 4:00 p.m.

Construction crews will work to:

  • Install and furnish 1″ service lines
  • Install and furnish 2″ service lines
  • Install and furnish 6″ fire service

This project will further support in providing reliable and quality water.

Click here to view the construction notice.

This is a map showing that construction crews will be working on West 112th Street.

Recently Completed Projects

Del Aire
Felton Ave. from 121st St. to Stacy St., on 121st St., 122nd St., 123rd St., 123rd Pl., 124th St., 125th St., 126th St. from Tahoe Ave. to Felton Ave., on Costa Dr. and on Stacy St. from Bart Ave. to Felton Ave.

Investment: $2.6 Million

Project Timeline:
January 22, 2018 – late April 2018

Working Hours:
Monday – Friday (No weekends or holidays)
8:00 a.m. – 4:00 p.m.

Construction crews will work to:

  • Replace 6,780 ft. of existing water pipe
  • Install 12 fire hydrants
  • Install 222 new service lines

This new pipeline, with a larger diameter, will provide better pressure for each customer and allow greater flow rates for fire suppression.

Click here to view the construction notice.

This is a map showing that construction crews will be working onFelton Avenue from 121st Street to Stacy Street, on 121st Street, 122nd Street, 123rd Street, 123rd Place, 124th Street, 125th Street, 126th Street from Tahoe Avenue to Felton Avenue, on Costa Drive and on Stacy Street from Bart Avenue to Felton Avenue.

Lawndale
Hawthorne Blvd. between 163rd St. and 172nd St.

Investment: $3,900,000

Project Timeline:
December 11, 2017 – late April 2018

Working Hours:
Monday – Friday (No weekends or holidays)
7:00 a.m. – 5:00 p.m.

Construction crews will work to:

  • Replace 11,800 ft. of existing water pipe
  • Install 22 fire hydrants
  • Install 48 new service lines

This new pipeline will improve the hydraulics of the water system, provide more reliable service to our customers, and address the deficiencies regarding the leaks over the past five years, due to the age of the existing pipelines.

Click here to view the construction notice.

This is a map showing that construction crews will be working on Hawthorne Boulevard.

Gardena
13503 S. Vermont Ave.

Investment: $1,007,200

Project Timeline:
September 29, 2017 – February 2018

Working Hours:
Monday – Friday
8:00 a.m. – 4:00 p.m.

Construction crews will work to:

  • Install a water filtration system at the Southern Plant Site

This project will further support in providing reliable and quality water.

Latest Update:
Crews have finished pouring the foundation for filters in addition to the concrete ring wall for the backwash tank.

Click here to view the construction notice.

This is a map showing that construction crews will be working on 13503 South Vermont Avenue, Gardena, California 90247.

Compton
Central Ave., Tajuata Ave., 151st St., 152nd St., 153rd St., 154th St., and 155th St.

Project Timeline:
August 15, 2017 – February 2018

Working Hours:
Monday – Friday
8 a.m. – 4 p.m.

Construction crews will work to:

  • Replace existing water pipeline
  • Install new fire hydrants
  • Install new service lines

Click here to view the construction notice.

This is a map showing that construction crews will be working on Central Avenue, Tajuata Avenue, 151st Street, 152nd Street, 153rd Street, 154th Street, and 155th Street.

Hawthorne
145th St., 146th St., 147th St., 148th St., 148th Pl., 149th St., Gerkin Ave., Cordary Ave., Florwood Ave., Doty Ave., Bodger Ave., Fonthill Ave., Kornblum Ave. and Cranbrook Ave., encompassed by Marine Ave. to Rosecrans and Prairie Ave. to Yukon Ave

Project Timeline:
May 8, 2017 – February 2018

Working Hours:
Monday – Friday
8:30 a.m. – 4 p.m.

Construction crews will work to:

  • Replace existing water pipeline
  • Install new fire hydrants
  • Install new service lines

Click here to view the construction notice.

This is a map showing that construction crews will be working on 145th Street, 146th Street, 147th Street, 148th Street, 148th Place, 149th Street, Gerkin Avenue, Cordary Avenue, Florwood Avenue, Doty Avenue, Bodger Avenue, Fonthill Avenue, Kornblum Avenue and Cranbrook Avenue, encompassed by Marine Avenue to Rosecrans and Prairie Avenue to Yukon Avenue.

Los Angeles
113th St., Denker Ave., and 110th Pl.

Project Timeline:
May 15, 2017 – January 2018

Working Hours:
Monday – Friday
8 a.m. – 4 p.m.

Construction crews will work to:

  • Replace existing water pipeline
  • Install new service lines

Click here to view the construction notice.

This is a map showing that construction crews will be working on Denker Avenue, 110th Place and 113th Street within the boundaries of 109th Street, Normandie Avenue, Imperial Highway and Hobart Boulevard.

Hawthorne
142nd St., 141st St., 140th St., 138th Pl., 138th St., 137th St., 137th Pl., Judah Ave., Rossburn Ave., Grider Ave., and Isis Ave.

Project Timeline:
June 16, 2017 – January 2018

Working Hours:
Monday – Friday
8:30 a.m. – 3:30 p.m.

Construction crews will work to:

  • Replace 9,970 ft. of water pipe
  • Install new fire hydrants
  • Install new service lines

Click here to view the construction notice.

This is a map showing that construction crews will be working on
Hawthorne
116th St.

Project Timeline:
September 28, 2017 – January 2018

Working Hours:
Monday – Friday
8:30 a.m. – 3:30 p.m.

Construction crews will work to:

  • Replace 780 ft. of existing water pipe
  • Install 1 fire hydrant
  • Install 13 new service lines

This project will relocate the water pipe and service lines, so they could be serviced and maintained without disturbing customer property.

Click here to view the construction notice.

This is a map showing that construction crews will be working on 116th Street.

Water System

Project Timeline:
April 20, 2017 – late June 2017

Working Hours:
8 a.m. – 4 p.m.

Construction crews will work to:

  • Disassemble the Wadsworth Plant, East Reservoir

Click here to view the construction notice.

This is a map showing that construction crews will be working on 14919 South Wadsworth Avenue.

*This list highlights some of the significant infrastructure projects in the Southwest Customer Service Area.