Capital Projects

Post
photograph of Pomello Plant project sitephotograph of Pomello Plant project site

GRC 2020 General Case (2022-24)

The General Rate Case approved June 29, 2023, invests over $15 million in the Claremont Customer Service Area. The new rates are being invested in your service area’s reservoir interior coating, new booster pumps, cathodic protection systems, and backup power equipment.

GRC 2023 General Case (2025-27)

The rates proposed for 2025-2027 will provide customers with long-term value by investing over $26.1 million in proactive capital investments and maintenance of local water infrastructure essential to the delivery and treatment of reliable, quality water. Investments in the Claremont Service Area include but are not limited to upgrading water distribution infrastructure, plant sites and water treatment facilities, the design/permitting of a new well, new systemwide technology to efficiently maintain reliable operation of the water system and the replacement of aging water mains and meters, main pumps, water purification and safety equipment.

Current & Upcoming Projects

Recently Completed Projects

outline of the Pomello Plant Project

Pomello Plant
928 E. Pomello Drive

Investment:
$1.9 million

Project Timeline:
(delayed due to COVID-19) October 14, 2019 – May 2021

Working Hours:
7 a.m. – 5 p.m.

Construction crews will work to construct a new groundwater well.

This project will provide a new groundwater source for the local water system and ensure Golden State Water can continue providing reliable water service to local customers.

Click here to learn more.

View the construction notice to learn more.

outline of Part 1 of Yale Avenue Project

Claremont
Yale Ave.

Investment:
$1,061,648

Construction crews worked to:

  • Replace approximately 3,600 ft. of aged water pipe
  • Install new service lines
  • Install fire hydrants

Part 1: 1st St. to Harrison Ave.

Project Timeline:
June 6, 2017 – mid-July 2017

View the construction notice.

outline of Part 2 of Yale Avenue Project

Part 2: Harrison Ave. to 7th St.

Project Timeline:
Mid-July 2017 – August 25, 2017

View the construction notice.

Claremont
Foothill Blvd. between Towne Ave. and Mountain Ave.

Project Timeline:
March 28, 2017 – end of April 2017

outline of Foothill Boulevard Project

Working Hours:
7 a.m. – 5 p.m.

Construction crews worked to:

  • Upgrade a fire hydrant
  • Install new service line

View the construction notice.