Capital Projects

Post

More than $650,000 in infrastructure improvements are planned for 2020 in the Clearlake service area.

The 2020 investments include water supply enhancements, distribution and ongoing improvements designed to replace old meters, mains and safety equipment. Click here to learn more and access a list of projects planned for 2020.

Current & Upcoming Projects

Sonoma & Lakeshore VFDs

Investment:
$460,000

Project Timeline:
June 24, 2019 – Feb. 5, 2020

Working Hours:
Monday – Friday (No weekends or holidays)
7 a.m. – 5 p.m.

Construction crews will work to install six Variable Frequency Drives (VFD).

This project will optimize the water treatment process and ensure Golden State Water can continue providing quality water service to local customers.
 

Recently Completed Projects

Napa Street Pipeline

Investment:
$320,000

Project Timeline:
Dec. 20, 2019 – Feb. 3, 2020

Working Hours:
Monday – Friday (No weekends or holidays)
7 a.m. – 5 p.m.

Construction crews worked to:

  • Install 800 LF of pipeline
  • Install 1 fire hydrant
  • Install 9 services

This project will improve the distribution system and ensure Golden State Water can continue providing reliable water service to local customers.

outline of Lower Lakeshore Pipeline Project

Lower Lakeshore Pipeline
The following streets will be affected: parts of Lower Lakeshore Dr., Lakeshore Dr. and Colusa St.

Investment:
$585,000

Project Timeline:
November 2018 – February 2019

Working Hours:
Monday – Friday (No weekends or holidays)
8 a.m. – 5 p.m.

Construction crews will work to:

  • Install 2,000 LF of pipeline
  • Install 3 fire hydrants
  • Install 34 services

This project will improve the distribution system and ensure Golden State Water can continue providing reliable water service to local customers.
 

outline of Crandall & Hill Pipeline Project

Crandall & Hill Pipeline
The following streets will be affected: parts of Crandall Ave. and Hillcrest Ave.

Investment:
$600,000

Project Timeline:
December 2018 – March 2019

Working Hours:
Monday – Friday (No weekends or holidays)
8 a.m. – 5 p.m.

Construction crews worked to:

  • Install 1,000 LF of pipeline
  • Install 2 fire hydrants
  • Install 39 services

This project will improve the distribution system and ensure Golden State Water can continue providing reliable water service to local customers.
 

Lakeshore Plant

Investment:
$115,000

Working Hours:
Monday – Friday (No weekends or holidays)
8 a.m. – 5 p.m.

Construction crews worked to install an emergency generator.

This project will ensure Golden State Water can continue providing reliable water service to local customers during a power outage.