Capital Projects

Post

More than $2.7 million in infrastructure improvements are planned for 2020 in the Los Alamitos service area.

The 2020 investments include water supply enhancements, distribution and ongoing improvements designed to replace old meters, mains and safety equipment. Click here to learn more and access a list of projects planned for 2020.

Current & Upcoming Projects

Lanett Area Main Replacement Project
The following streets will be affected: Lanett St., between New York Ave. and Alaska Ave.; cul-de-sac’s Lolina Lane and New Mexico Lane; Belday St., between New York Ave and Alaska; and New York Ave. from Moody St. to end of the street.

Investment:
$1.9 million

Project Timeline:
June 22, 2020 – October 2020

Working Hours:
Monday – Friday
7:30 a.m. – 4 p.m.

Construction crews will work to:

  • Replace 3,500 LF of older 6-inch & 4-inch pipes with new 8-inch pipe
  • Install 10 hydrants
  • Install 86 services

This project will improve the distribution system and ensure Golden State Water can continue providing reliable water service to local customers.

View the construction notice.

View the presentation to Cypress City Council.

outline of Howard Avenue Project

Howard Ave. Main Replacement

We appreciate the community’s patience as crews worked to complete the first phase of the project, which was delayed by wet weather and other unanticipated challenges.

Phase 2:
Scheduled to begin in the second quarter of 2020. During this phase, crews will work to construct individual house lines to the new meter locations along the street frontage in order to abandon the old alleyway main located north of Howard Avenue between Reagan and Bloomfield.

Phase 3:
The schedule for the final phase of construction has not yet been determined. During this phase, crews will work to construct house lines and abandon the alleyway main located north of Howard between Bloomfield Street and Lexington Drive.

Investment:
$2.8 million

Project Timeline:
November 5, 2018 – TBD

Working Hours:
Monday – Friday
7:30 a.m. – 5 p.m.

Construction crews will work to:

  • Install 7,500 LF of pipeline
  • Install 7 hydrants
  • Install 181 services

This project will improve the distribution system and ensure Golden State Water can continue providing reliable water service to local customers.

Click here for more information on this project.

View the construction notice for Howard Avenue.

View the construction notice for Farquhar Avenue.

Recently Completed Projects

outline of Fern Street Project

Fern Street Main Replacement
The following streets will be affected: Fern Street; parts of Stanford Avenue; parts of Sycamore Street; parts of Court Street; parts of Acacia Avenue; and parts of Garden Grove Boulevard

Investment:
$1.25 million

Project Timeline:
February 6, 2019 – Aug. 16, 2019

Working Hours:
9 a.m. – 3 p.m. on major streets
7 a.m. to 5 p.m. otherwise

Construction crews will work to:

  • Install 4,000 LF of pipeline
  • Install 4 hydrants
  • Install 64 services

This project will improve the distribution system and ensure Golden State Water can continue providing reliable water service to local customers.

View the construction notice.
 

outline of Florista West Project

Florista West Tank
10852 Cherry St.

Investment:
$742,300

Project Timeline:
June 18, 2017 – November 2018

Working Hours:
Monday – Friday
8 a.m. – 5 p.m.

Construction crews worked to:

  • Recoat the interior of a 1.5 million gallon reservoir
  • Install safety appurtenances on the interior and exterior of the reservoir

These improvements extend the useful life of the reservoirs and allow for their continued safe operation, enabling Golden State Water Company to continue to provide reliable, quality water to our customers.

View the construction notice.
 

Lowden Well
10552 Lowden St.

Project Timeline:
May 23, 2018 – June 1, 2018

Working Hours:
Monday to Friday

8 a.m. – 5 p.m.

Construction crews are working to:

  • Install new pump equipment for Lowden Well

View the construction notice.