Capital Projects

Post

2026 General Rate Case (2028-30)

The rates proposed for 2028-2030 will provide customers in the Arden-Cordova Service Area with long-term value by investing nearly $23 million in local water infrastructure essential to delivering safe, high-quality, and reliable drinking water. 

Proposed investments include acquiring property for a future groundwater well, a 0.45-million-gallon water storage tank, and a booster pump station, replacing the aging Coloma Reservoir No. 1, upgrading filtration systems at the Coloma Water Treatment Plant, and constructing two new 0.20-million-gallon reservoirs, a booster pump station, and backup power equipment at the James Plant. These projects, combined with ongoing pipeline replacements throughout the service area, will improve water quality, add nearly one million gallons of storage capacity, strengthen system reliability, and extend the life of critical water infrastructure. Together with the company’s ongoing investments in water treatment technology and fire hydrants that support public safety, new investments will help maintain safe drinking water standards and reliable service for the community.

For frequently asked questions about the rate-making process, click here

Learn about the infrastructure investments in the water system serving your community’s homes and businesses: Arden Cordova 2028-30 Proposed GRC.

Current & Upcoming Projects

Recently Completed Projects

Church Well 25 Project

Location: 10400 Coloma Road, behind Cordova Lutheran Church.

Project Timeline:
July 2023 – Early 2024 (weather permitting)

Working Hours:
Monday – Friday (No weekends or holidays)
8:30 a.m. – 4:30 p.m.

Construction crews will work to:

  • Install well equipment and perform site improvements.

This project will ensure Golden State Water can continue providing reliable water service to local customers.

View the Construction Notice.

Pipeline Installation Project

Location: Southbound on Watt Avenue from Barrington Rd to Northrop Ave, and 500’ into the streets of the intersections at Barrington Rd, Hyde Way, Hurley Way, Ardenridge Dr, Humboldt Way, Windsor Dr, Wemberley Dr, Mayfair Dr, Tembrook Dr, Wellington Dr, and Northrop Ave.

Project Timeline:
September 2023 – March 2024

Working Hours:

Day Shift:
Monday – Friday (No weekends or holidays)
8:00 a.m. – 3:30 p.m.

Night Shift:
Monday – Thursday (No weekends or holidays)
9:00 p.m. – 5:00 a.m.

Construction crews will work to:

  • Install a new water pipeline

This project will ensure Golden State Water can continue providing reliable water service to local customers.

View the Construction Notice.

Trussel Plant
East end of Trussel Way in Arden

Investment:
$2.6 million

Project Timeline:
Feb. 4, 2019 – Jan. 22, 2020

Working Hours:
Monday – Friday (No weekends or holidays)
8 a.m. – 5 p.m.

Construction crews will work to:

  • Construct groundwater well
  • Construct 400,000-gallon water storage tank
  • Install 3 booster pumps
  • Install 1 generator
  • Construct disinfection building
  • Execute necessary street improvements

This project will improve the distribution system and ensure Golden State Water can continue providing reliable water service to local customers.

Click here to view the construction notice.
 

Coloma Reservoir
Cordova system of the Arden-Cordova customer service area

Investment:
$1.58 million

Project Timeline:
Oct. 16, 2018 – January 2020

Construction crews worked to:

  • Recoat interior of Coloma Reservoir No. 3 and the clarifier
  • Conduct structural and safety improvements to the reservoir and clarifier
  • This project will ensure Golden State Water can continue providing reliable water service to local customers.

outline of Rancho Cordova Folsom Blvd Project

Rancho Cordova
Folsom Blvd. from Zinfandel Dr. to Don Juan Dr. and McGregor Dr. to Hwy. 50

Investment:
$900,000

Project Timeline:
Nov. 6, 2018 – June 11, 2019

Working Hours:
Monday – Friday (No weekends or holidays)
8:30 a.m. – 3:30 p.m.

Construction crews worked to:

  • Install 500 LF of 16-inch pipeline
  • Install 1,270 LF of 12-inch pipeline
  • Install 135 LF of 8-inch pipeline
  • Install 3 fire hydrants

This project will improve the distribution system and ensure Golden State Water can continue providing reliable water service to local customers.
 

outline of Rancho Cordova Saltana Way Project

Rancho Cordova
Saltana Way, Croetto Way, Furmint Way and Woodberry Way

Investment:
$1.3 million

Project Timeline:
October 15, 2018 – December 2018

Working Hours:
Monday – Friday (No weekends or holidays)
8 a.m. – 5 p.m.

Construction crews worked to:

  • Install 2,800 LF of pipeline
  • Install 7 fire hydrants
  • Install 41 services

This project will improve the distribution system and ensure Golden State Water can continue providing reliable water service to local customers.

Click here to view the construction notice.
 

outline of Rancho Cordova Pedro Way Project

Rancho Cordova
Pedro Way, Malbec Ct., and Zinfandel Dr. from Alicante Way to Barbera Way

Investment:
$965,000

Project Timeline:
October 25, 2017 – March 2018

Working Hours:
Monday – Friday
7 a.m. – 5 p.m.

Construction crews worked to:

  • Install approximately 5,800 ft. of water pipe
  • Connect new water pipe to existing pipes

This installation replaced a 50-year old steel pipe, improved the hydraulics of the water system and provided more reliable service to our customers.

Click here to view the construction notice.
 

outline of Rancho Cordova Folsom Blvd/Sunrise Ave Project

Rancho Cordova
North of Folsom Blvd. and West of Sunrise Ave.

Project Timeline:
June 5, 2017 – September 8, 2017

Working Hours:
Monday – Friday
7 a.m. – 5 p.m.

Construction crews worked to:

  • Install approximately 141 water meters in both front and back yards

Click here to view the construction notice.