More than $8.9 million in infrastructure improvements are planned for 2022 in the Barstow service area.

The 2022 investments include water supply enhancements, distribution and ongoing improvements designed to replace old meters, mains and safety equipment. Click here to learn more and access a list of projects planned for 2022.

Current & Upcoming Projects

Irwin Transmission Main Project
Irwin Road from Gabilan Street to Barstow Road

Project Timeline:
December 20, 2021 – Late January 2022

Construction crews worked to:

  • Install 5,700 ft. of new water pipe

View the construction notice.

Recently Completed Projects

outline of Crooks Ave Barstow Project

Barstow
Crooks Ave. and Pierce Ave.

Project Timeline:
July 5, 2017 – August 18, 2017

Construction crews worked to:

  • Install 1,700 ft. of new water pipe
  • Install 10 new service lines
  • Install 4 fire hydrants

View the construction notice.
 

outline of Barstow Avenues A, B & C Project

Ave. A, Ave. B, & Ave. C
Between Flora Ave. and Keith St.

Project Timeline:
May 8, 2017 – June 20, 2017

Working Hours:
7 a.m. – 4:30 p.m.

Construction crews worked to:

  • Install 450 ft. of new water pipe
  • Install 5 new service lines
  • Install 1 fire hydrant

View the construction notice.
 

outline of Barstow Heights Project

Barstow Heights
Highview Ave., N St. and O St.

Project Timeline:
November 7, 2016 – mid-April 2017

Working Hours:
7 a.m. – 4 p.m.

Construction crews worked to:

  • Install 11,500 ft. of new water pipe
  • Install 72 new service lines
  • Install 13 fire hydrants

View the construction notice.
 

outline of Barstow Rimrock Rd Project

Barstow
Rimrock Rd., Armory Rd., G St. and D St.

Project Timeline:
September 9, 2016 – January 2017

Working Hours:
7 a.m. – 4 p.m.

Construction crews worked to:

  • Install 11,500 ft. of new water pipe
  • Install 78 new service lines
  • Install 12 fire hydrants

View the construction notice.