Capital Projects
2026 General Rate Case (2028-30)
The rates proposed for 2028-2030 will provide customers in the Simi Valley Service Area with long-term value by investing nearly $32 million in local water infrastructure essential to delivering safe, high-quality, and reliable drinking water.
Proposed investments include installing a new inline booster station with two 500-gallon-per-minute pumps to improve service to the Katherine Zone, recoating and upgrading the 1.50-million-gallon Alamo Reservoir, and replacing over 280 service lines throughout the customer service area. These projects, combined with ongoing pipeline replacements throughout the service area, will improve water quality, strengthen system reliability, and extend the life of critical storage infrastructure. Together with the company’s ongoing investments in water treatment technology and fire hydrants that support public safety, new investments will help maintain safe drinking water standards and reliable service for the community.
For frequently asked questions about the rate-making process, click here.
Learn about the infrastructure investments in the water system serving your community’s homes and businesses: Simi Valley 2028-30 Proposed GRC.
Current & Upcoming Projects
Clover St and Angela St Area Main Replacement
Location: Construction will occur on portions of Clover Street, Lupin Street, Magnolia Street, and Angela Street.
Project Timeline:
July 2026 – October 2026
Working Hours:
Monday – Friday (No weekends or holidays)
7:00 a.m. – 3:30 p.m.
Construction crews will work to:
-
Install approximately 2,800 feet of water main.
This project will ensure Golden State Water can continue providing reliable water service to local customers.
View the Construction Notice.
Recently Completed Projects
Water Main Improvements
Location: Construction will occur on Sequoia Ave, Royal Ave, Shenandoah Ave, Acadia St, Olympic St, Blackstock Ave, Glacier St, Crater St, Barnes St, and Moreno Dr.
Project Timeline:
April 2024 – October 2024
Working Hours:
Monday – Friday (No weekends or holidays)
7:00 a.m. – 3:30 p.m.
Construction crews will work to:
-
Install new 8-in PVC Water Main and new service lines.
This project will ensure Golden State Water can continue providing reliable water service to local customers.
View the Construction Notice.
Sycamore Drive Pipeline Project
Investment: Over $1.5 million
Project Location: The intersection of E. Los Angeles Avenue and Sycamore Drive.
Project Timeline:
June 13, 2022 – July 29, 2022
Working Hours: June 13 – June 23
Monday – Sunday
10 p.m. – 6:00 a.m.
Working Hours: June 23 - July 29
Monday – Friday
10 p.m. – 6:00 a.m.
Construction crews will work to install a new pipeline.
The project will improve system hydraulics and increase water service reliability.
View the Construction Notice.
Sycamore Drive & Niles Discharge Pipe
Investment:
$500,000
Project Timeline:
July 29, 2019 – end of Sept. 27, 2019
Working Hours:
Monday – Friday
7 a.m. – 3:30 p.m.
Construction crews will work to install 1,020 LF of pipeline.
This project will improve the distribution system and ensure Golden State Water can continue providing reliable water service to local customers.
View the Construction Notice.
Portable Generator
Systemwide
Investment:
$735,000
Project Timeline:
Sept. 30, 2019 – Nov. 13, 2019
Working Hours:
Monday – Friday, 7 a.m. – 4 p.m.
Construction crews will work to install emergency generators throughout the system.
This project will ensure Golden State Water can continue providing reliable water service to local customers during site-specific power outages.
View the Construction Notice.
Royal Ave. Bridge
Royal Avenue bridge at the Arroyo Simi channel crossing
Investment:
$361,000
Project Timeline:
September 21, 2018 – November 30, 2018
Working Hours:
Monday – Friday (No weekends or holidays)
7:00 a.m. – 4:00 p.m.
Construction crews worked to install 150 LF of 8″ main.
This project will improve the distribution system and ensure Golden State Water can continue providing reliable water service to local customers.
View the Construction Notice.
Lautenschlager Plant
Simi Valley system
Investment:
$550,000
Project Timeline:
June 1, 2018 – December 1, 2018
Working Hours:
Monday – Friday (No weekends or holidays)
7:00 a.m. – 4:00 p.m.
Construction crews worked to recoat the Lautenschlager Plant steel tank.
This project will ensure Golden State Water can continue
providing reliable water service to local customers.
Niles Forebay
Simi Valley system
Investment:
$281,200
Project Timeline:
May 28, 2018 – December 11, 2018
Working Hours:
Monday – Friday (No weekends or holidays)
8 a.m. – 5 p.m.
Construction crews will work to replace the existing tank with a new 40,000 gallon tank.
This project will ensure Golden State Water can continue
providing reliable water service to local customers.
Simi Valley
Sandalwood Dr.
Project Timeline:
August 28, 2017 – February 2018
Working Hours:
7 a.m. – 4 p.m.
Construction crews worked to recoat the Lauenschalger Plant Tank 2.
View the Construction Notice.


