Capital Projects
More than $350,000 in infrastructure improvements are planned for 2020 in the Simi Valley service area.
The 2020 investments include water supply enhancements, distribution and ongoing improvements designed to replace old meters, mains and safety equipment. Click here to learn more and access a list of projects planned for 2020.
Current & Upcoming Projects
This section is currently under construction. Please check regularly for the latest updates!
Recently Completed Projects
Sycamore Drive & Niles Discharge Pipe
Investment:
$500,000
Project Timeline:
July 29, 2019 – end of Sept. 27, 2019
Working Hours:
Monday – Friday
7 a.m. – 3:30 p.m.
Construction crews will work to install 1,020 LF of pipeline.
This project will improve the distribution system and ensure Golden State Water can continue providing reliable water service to local customers.
View the construction notice.
Portable Generator
Systemwide
Investment:
$735,000
Project Timeline:
Sept. 30, 2019 – Nov. 13, 2019
Working Hours:
Monday – Friday, 7 a.m. – 4 p.m.
Construction crews will work to install emergency generators throughout the system.
This project will ensure Golden State Water can continue providing reliable water service to local customers during site-specific power outages.
View the construction notice.
Royal Ave. Bridge
Royal Avenue bridge at the Arroyo Simi channel crossing
Investment:
$361,000
Project Timeline:
September 21, 2018 – November 30, 2018
Working Hours:
Monday – Friday (No weekends or holidays)
7:00 a.m. – 4:00 p.m.
Construction crews worked to install 150 LF of 8″ main.
This project will improve the distribution system and ensure Golden State Water can continue providing reliable water service to local customers.
View the construction notice.
Lautenschlager Plant
Simi Valley system
Investment:
$550,000
Project Timeline:
June 1, 2018 – December 1, 2018
Working Hours:
Monday – Friday (No weekends or holidays)
7:00 a.m. – 4:00 p.m.
Construction crews worked to recoat the Lautenschlager Plant steel tank.
This project will ensure Golden State Water can continue
providing reliable water service to local customers.
Niles Forebay
Simi Valley system
Investment:
$281,200
Project Timeline:
May 28, 2018 – December 11, 2018
Working Hours:
Monday – Friday (No weekends or holidays)
8 a.m. – 5 p.m.
Construction crews will work to replace the existing tank with a new 40,000 gallon tank.
This project will ensure Golden State Water can continue
providing reliable water service to local customers.
Simi Valley
Sandalwood Dr.
Project Timeline:
August 28, 2017 – February 2018
Working Hours:
7 a.m. – 4 p.m.
Construction crews worked to recoat the Lauenschalger Plant Tank 2.
View the construction notice.