Capital Projects
More than $6.8 million in infrastructure improvements are planned for 2022 in the Simi Valley service area.
The 2022 investments include water supply enhancements, distribution and ongoing improvements designed to replace old meters, mains and safety equipment. Click here to learn more and access a list of projects planned for 2022.
Current & Upcoming Projects
Sycamore Drive Pipeline Project
Investment: Over $1.5 million
Project Location: The intersection of E. Los Angeles Avenue and Sycamore Drive.
Project Timeline:
June 13, 2022 – July 29, 2022
Working Hours: June 13 – June 23
Monday – Sunday
10 p.m. – 6:00 a.m.
Working Hours: June 23 - July 29
Monday – Friday
10 p.m. – 6:00 a.m.
Construction crews will work to install a new pipeline.
The project will improve system hydraulics and increase water service reliability.
View the here.
Recently Completed Projects
Sycamore Drive & Niles Discharge Pipe
Investment:
$500,000
Project Timeline:
July 29, 2019 – end of Sept. 27, 2019
Working Hours:
Monday – Friday
7 a.m. – 3:30 p.m.
Construction crews will work to install 1,020 LF of pipeline.
This project will improve the distribution system and ensure Golden State Water can continue providing reliable water service to local customers.
View the construction notice.
Portable Generator
Systemwide
Investment:
$735,000
Project Timeline:
Sept. 30, 2019 – Nov. 13, 2019
Working Hours:
Monday – Friday, 7 a.m. – 4 p.m.
Construction crews will work to install emergency generators throughout the system.
This project will ensure Golden State Water can continue providing reliable water service to local customers during site-specific power outages.
View the construction notice.
Royal Ave. Bridge
Royal Avenue bridge at the Arroyo Simi channel crossing
Investment:
$361,000
Project Timeline:
September 21, 2018 – November 30, 2018
Working Hours:
Monday – Friday (No weekends or holidays)
7:00 a.m. – 4:00 p.m.
Construction crews worked to install 150 LF of 8″ main.
This project will improve the distribution system and ensure Golden State Water can continue providing reliable water service to local customers.
View the construction notice.
Lautenschlager Plant
Simi Valley system
Investment:
$550,000
Project Timeline:
June 1, 2018 – December 1, 2018
Working Hours:
Monday – Friday (No weekends or holidays)
7:00 a.m. – 4:00 p.m.
Construction crews worked to recoat the Lautenschlager Plant steel tank.
This project will ensure Golden State Water can continue
providing reliable water service to local customers.
Niles Forebay
Simi Valley system
Investment:
$281,200
Project Timeline:
May 28, 2018 – December 11, 2018
Working Hours:
Monday – Friday (No weekends or holidays)
8 a.m. – 5 p.m.
Construction crews will work to replace the existing tank with a new 40,000 gallon tank.
This project will ensure Golden State Water can continue
providing reliable water service to local customers.
Simi Valley
Sandalwood Dr.
Project Timeline:
August 28, 2017 – February 2018
Working Hours:
7 a.m. – 4 p.m.
Construction crews worked to recoat the Lauenschalger Plant Tank 2.
View the construction notice.